The interview with Sarina Arcari, Staff Vice President of Implementation Management Office (PMO) at WellPoint Inc. (since December 2014, Anthem Inc.).


I have heard that at the beginning you had some problems with everyone doing schedules and reporting in different formats. How did you manage to ensure standardization of PM tools in your company? Usually, it is very painful when it comes to implementing tools, everyone complains about having to do additional work, about not having licenses and so on…

One of the best things for me about belonging to PMI is being able to talk to people from all over the world who have exactly the same problems as I have. Oh, thank God, it is not just me!

So how did we do it? When I got there we had nothing. There was no MS Project, nothing. They had Excel spreadsheets, everybody had a different one, and there was a big giant mess. I had experience using MS Project but not a lot, certainly not doing schedules on a scale that we do them now. But I had some experience. So I knew that MS Project was sort of a standard for project management tool. Besides, we were a Microsoft company, meaning that we had Microsoft Office and other tools on our desktop. So I thought MS Project was going to be the easiest sell. It was going to cost us money but I only asked for six licenses at the beginning as I only had six project managers. So that is where I started.

Next, I went to the PMI chapter and I said:

„I need to know who the best MS Project expert is in Hampton Road”

which is the area of our PMI chapter geography. It turned out that, miracle of miracles, he was coming to speak in our chapter the following week. So I went to the chapter meeting, I met the guy and I actually convinced him to start running MS Project training courses at his facility but for a price that I could afford. And I told him that I would send my people only there if he would did this training for us. And so to this date I send all of my people to him and I recommend everybody in the company send their people. It is 2 days for 8 hours training course when he teaches all of them MS Project basics and how to build WBS-based project schedule. So we started with ourselves, just the six of us.

How did you do scheduling and reporting with only six people knowing MS Project?

We would go and sit with every Subject Matter Expert when we started a project with our laptop and we would build their schedule with them from scratch, every time. They would tell us the tasks and we would put them in. And then every week we would print out their tasks, we would scan that and email it to them. They would print it, they would write in their percent complete, they would send it back to us and we would have people type it into the schedule so that we could keep it. That is insane but this is how we started.

And then it just evolved. At first, we were sitting there doing scheduling for Subject Matter Experts. They could not really refuse to do it, because we were not asking them to do it. They would sit there and time after time we would be doing the same thing. And one day they said „Come on, we can do this ourselves.” And I said „You are going to have to spend $800 for a license” but they replied „Oh, it is not so bad.” So slowly but surely people started doing that. Couple of them even got their PMPs. They were like „I am really a Project Manager, aren’t I?”, „Yes, you are.” That was a surprise for people but this is actually what they were doing. Yes, they were experts but they were executing tasks in their departments. So it took couple of years but it caught on.

What are the next challenges for a PMO in an organization that grew so fast?

When you go from 6 people to a hundred people what I am finding is that the organizational structure that we had is not sufficient because everybody has got too many projects. Some of the fundamentals are slipping and I don’t want to see that. So we are right now going through an exercise of how do we take these hundred people and organize them in a way where each portfolio manager can be that strategic coach and guide and mentor that we need when we have got this many people and this many projects going on.

When I was running the IMO myself I had 4 portfolio managers and each probably had 5 or 6 people, maybe 2 or 3 projects, maybe one megaproject. But now we have got 25 projects and a hundred people so I probably need to flatten the organization out so that we can still maintain that attention to details that we’ve became known for in terms of execution.

We got too big too fast. We grew by 48 percent last year and I need to make an adjustment quickly before we start slipping on places where it is fundamental. And we should not be slipping just because people are too busy and are not getting enough close guidance. So I want to flatten up the organization.

Last final question if I may. For the companies in Poland who can be interested in applying for a PMO of the Year award, could you say couple of words about how did the application process looks like?

First you have to be sponsored by a senior executive in your company. They have to be the person nominating you. You have 10 pages to tell your story. It is a very short application process although we spent 5 months making sure that those 10 pages tell the best possible story that we could. We run it as a project.

The first call I made was to our Chief Operating Officer and I said:

„Listen, there is this PMO of the Year award. I went to the PMO Symposium, saw the person who won the award in 2013. They have very impressive results but not more impressive than what we do here. I think we could win the award. And here is what it means for the company… in our proposals that we write to win our business, we could say that we are an award winning implementation office, if we win this award.”

He liked that and asked what we had to do. So I said „Here is the rules, here is what we have to do.” He said „You tell me what I need to say, I review it, I put my own color in it and then we will call it good.” So we decided to run for it and write up a story.

We are a government contractor, we have to bid on all of our business as a company. So we do these very robust proposals, 5-6 inches deep of paper, to tell our story and win our business. We took that approach. We did a lot of research on numbers and we got our proposal team to help us make it look pretty. So we had some pretty graphs and charts, and pictures. But we did not want it to take up too much space because you only get 10 pages.

We did about 8 pages and we sent it over to our executive asking him what else he wanted to say. And he was amazing. He wrote about a page and a half about how we were a strategic asset for the company and we would never have been able to grow if it weren’t for the PMO. I could not have it written better for him. He just said probably everything that the PMI wanted to hear. And that was awesome.

What happened after you submitted the application?

We submitted it by the June 1st. In August I got a phone call. I was sitting at my desk and someone told me „Mark Langley is on the phone.” And I was like „Yeah, right. That’s very funny.” But it was Mark Langley! He said:

„I just want to congratulate you, you’ve been selected as a top three finalist. Someone from my office is going to be calling you and telling more.”

PMI contract is with a vendor that does videos and writes the stories for the PMI magazine and all that kind of stuff. So they made an arrangements to come out to our offices. They stayed for three days and they shot the video, they took still photographs for the magazine and interviewed us. They actually interviewed all of the finalists and never told us who won. I did not know we won until I was sitting in that room at PMO Symposium.

Thank you a lot for the interview.

The interview was conducted by Marta Bobińska (TenStep Polska) in January 2015.